Alternative Brazing for Shipboard Use

Shipbuilding costs are expected to be reduced by brazing pipe joints shipboard with a small, lightweight heating system as opposed to the current method of torch brazing. NMC photo

Objective

The goal of this Navy Metalworking Center (NMC) project was to develop alternative flame brazing technology to be used on the majority of CVN 68 and CVN 78 Class aircraft carriers and VIRGINIA Class (SSN 774) submarine (VCS) construction fittings to address these problems.

Background

Like most shipyards, Huntington Ingalls Industries - Newport News Shipbuilding (HHI-NNS) uses a hand-held torch to manually flame braze fittings shipboard. This method is labor- intensive due to the time required to reach the melting temperature of the filler material. Additionally, the process causes occasional paint damage as it is difficult to control the flame and negotiate the minimal clearances that may exist surrounding the fitting. The limited clearance also makes it difficult to manipulate the torch to achieve a uniform bond, which causes occasional pipe leaks. Paint damage and pipe leaks result in rework that further adds cost.

Technical Approach

The new flame brazing technology uses a programmable logic controller, mass flow controllers, and a specially designed burner to surround the fitting.

Benefits

Using alternative flame brazing technology in this application will reduce the time required to braze each joint, as well as the amount of rework related to manual torch brazing. In addition, the alternative flame brazing technology will reduce training time and the need for highly skilled operators due to user-friendly operation. This will translate into significant labor and production cost savings. Implementing this alternative brazing technology at NNS will result in an estimated cost savings of $2.6M in the construction of three CVN and nine VCS hulls, and in the overhaul of seven CVN hulls. In addition, the proposed solution may benefit other platforms requiring flame brazing.

Implementation

NNS used the prototype flame brazing system developed during the NMC project to generate brazing procedures and qualification samples. NNS tested the qualification samples and provided the procedures and results to its Supervisor of Shipbuilding (SOS) for acceptance. SOS approved the alternative brazing procedure qualification in January 2012. The transfer of the prototype system to the PMS 378 Program Office signified that the alternative flame brazing technology is capable for use in CVN and VCS construction and can be implemented at NNS. In June 2012, NNS used the prototype brazing system to successfully braze production pipe joints in the construction of CVN 78. NNS also plans to purchase approximately 10 additional brazing systems from one of three companies interested in commercializing the technology.

Status

Completed

Stakeholder

Blenda Gately
PMS 378

Partners

Naval Surface Warfare Center, Carderock Division
Newport News Shipbuilding
PMS 378 Future Aircraft Carriers
PMS 450 Virginia Class Program Office
Lean Engineering